Big Mesa is in the process of completing three water system upgrade projects: (1) a direct pipeline from the filtration system facility to the storage tank, 2) a filtration system and 3) meter replacement with automatic meter reading is in design. Easements, bid documents,

schedules, and bid awards are planned to allow for fall/winter 2020 construction for meters and direct line start and 2nd quarter 2021 completion. The filtration system will be completed in the fall 2022. These projects will be accomplished with minimal interruptions to member’s water service. 

The meter replacement project was completed by Spring 2021. 